The following will be used in these
cases :
(a) After a shoot & pull job and prior to
p.o.o.h.
(b) To control & cure losses before a workover,
before pulling completion string in case string is not
parted or has holes in it,
or when pulling an E.S.P. pump out of hole
Mixing Procedure for Temperature
up to 250°F
Thixsal-Ultra Viscous
Carrier Fluid Preparation
Allow Pill to agitate for 10-15 mns prior to pumping downhole.
The Pill will be displaced downhole using Thixsal-Ultra
minimum 5bbls ahead and 10 bbls behind.
The Bridgesal-Ultra temp limitation
is 335°F Using the correct formula.
Pill volume normally needed is:
½ to 1 barrel per foot of open perfs + volume to
fill inside the casing from plug back total depth up to
+/- 100 to above top open perforation .
Note: The needed Thixsal-Ultra
as viscous fluid carrier ahead & behind should be mixed
using a concentration of 6 ppb in water .